Paving Works in Grand Canal
September 5, 2018
Out of courtesy Apleona Real Estate are provided all with an update of paving works in Grand Canal.
These works have been instructed by DCC.
Some areas are under the remit of DCC and some areas are under the remit of Grand Canal Harbour Management Ltd.
The granite is due to arrive 2nd week in October 2018 . Works are due to be complete mid to end of November 2018
- Sir John Rogerson Quay – Flagging complete Granite kerbing early November
- South Campshire – Flagging complete Granite kerbing early November
- Lazer Lane – Flagging complete COMPLETED
- Forbes Lane – Commence today 16th July to 29th July Flagging completed, granite at Marker Hotel mid October
- Blood Stoney Rd – Commence 30th July to 19th August COMPLETED
- Hibernian Rd – Commence 20th August to 2nd September, flagging will be completed by 15th September, granite kerbs early November
- Cardiff Lane – Commence 3rd September to 16th September, commence 24th September to 13th October
- Pearse Street – Commence 17th Sept to 23rd Sept Commence 15th to 27th October
- Hanover Quay – Commence 24th Sept to 7th Oct Flagging completed, granite setts and kerbs in November
- Misery Hill – Commence 8th Oct to 21st October Flagging outside Facebook 12th to 19th September, granite outside Marker mid October